Project Plan · Data Infrastructure

A governed tracking plan, wired to 4 destinations, in 54 hours.

Five phases to stand up Segment (or a Segment-like CDP) as the single source of event data — instrumenting tracking, wiring ads, product analytics, the warehouse, and CRM, then validating, activating, and documenting the result.

Role Authored this implementation plan — phase scoping, task breakdown, and effort estimation across Segment, ad/analytics destinations, and CRM

50–55 total hours 5 phases 4 destination integrations 1 CDP · Segment

Five phases, kickoff to handover

Each phase builds on the last: scope and accounts first, then the bulk of integration work, followed by validation, activation, and documentation.

1
Kick-Off 6h

Define scope, stakeholders, and destinations. Choose and configure Facebook, Mixpanel (or Amplitude), and Snowflake (or BigQuery); set up Segment account and workspace; map data points to schemas for each destination.

2
Implementation 30h

The bulk of the build: Segment tracking code on web/app, event and property mapping via Protocols, and integration setup across Facebook, Mixpanel (or Amplitude), Snowflake (or BigQuery), and a CRM platform (Braze, Salesforce, etc.).

3
Testing 9h

Validate tracking accuracy on web/app, confirm data flows correctly from Segment into each destination, and verify successful, discrepancy-free streaming into the data warehouse.

4
Data Utilisation & Analysis 4h

Put the new data to work: build custom audiences in Facebook, set up engagement reports/dashboards in Mixpanel (or Amplitude), and run initial behavioural queries in Snowflake (or BigQuery).

5
Documentation & Training 5h

Document the implementation, integration configurations, and tracking setup; document the CRM integration; and train the team on using Segment, accessing destination data, and interpreting analytics.

What each phase covers, task by task

Phase 1 — Kick-Off

Phase 2 — Implementation

Phase 3 — Testing

Phase 4 — Data Utilisation & Analysis

Phase 5 — Documentation & Training

* Dependent on the Engineering Team.
** Dependent on required destinations.

Where the 54 hours go

54h
Total estimate
50–55h range
30h
Phase 2 — Implementation
~56% of total effort
9h
Phase 3 — Testing
Tracking, destinations, warehouse
4
Destinations wired
Facebook · Mixpanel/Amplitude · Snowflake/BigQuery · CRM

From ad-hoc instrumentation to one governed data source

⊕

Segment as the central CDP

A single tracking plan and schema feeds every downstream tool — replacing ad-hoc, per-destination instrumentation with one governed source of event data.

⚡

Facebook

Event mappings and custom audiences for ad targeting and conversion tracking.

↻

Mixpanel / Amplitude

Verified event flow and dashboards for product engagement analysis.

⟲

Snowflake / BigQuery

Continuous, validated data streaming into the warehouse for ad-hoc analysis.

✕

CRM (Braze, Salesforce, etc.)

User data sync and event tracking for lifecycle and retention messaging.